Kitchen Remodel Timeline: Every Step in Order, Week by Week

Noor K.Noor K.
Bright daytime kitchen mid-remodel: new white shaker base and wall cabinets installed and level, no countertops yet, freshly painted walls and a new light oak floor, ready for the countertop template

A typical kitchen remodel timeline runs about 6 to 12 weeks of work, not counting planning, and structural changes push it to 3 to 8 months, according to Fixr. Counted from the first measurement, with design and the cabinet order included, the two sample schedules below run about 10 and about 15 weeks.

The steps run in this order: measure, design, order cabinets, demolition, rough-in and inspection, drywall and floors, cabinet installation, countertop template and fabrication, then backsplash, appliances and the punch list.

The date that moves everything else is cabinet delivery: order early enough that the boxes are in the house by the rough-in inspection.

Key takeaways

  • Plan on about 6 to 12 weeks of construction for a remodel that keeps the layout; walls, plumbing moves and custom cabinets stretch it to several months.
  • Order cabinets before demolition, not after. Fabuwood stock series typically ship in 2 weeks; built-to-order lines such as Diamond and Decorá typically take 6 to 8 weeks.
  • A slow cabinet line does not have to mean more weeks without a kitchen: keep cooking in the old one and start demolition only once the order has a ship date.
  • Countertops are measured on installed cabinets, so every day the cabinets slip, the counters, sink and backsplash slip with them.
Table of Contents

How Long Does a Kitchen Remodel Take?

A kitchen remodel takes about 6 to 12 weeks of construction on average, and 3 to 8 months when walls or structure change, according to Fixr's remodel guide. Add design and ordering before that. The scope, not the size of the room, decides which end of the range you land on.

Published figures disagree because they measure different things. Fixr's 6 to 12 weeks leaves out planning and hiring a contractor. KraftMaid splits it into a construction start of a few days to 2 weeks and an installation stage of 4 to 6 weeks, and leaves planning at "as long as you need".

Homeowner surveys run much longer. The 2024 U.S. Houzz & Home Study found kitchens took the longest of any room in 2023: 9.6 months of planning and 5.1 months of building on average. Decisions, not labor, eat most of that calendar.

The first row is our own experience; the others are Fixr's figures:

Scope What changes Typical construction time Source
Cabinets and counters only, same layout Boxes, tops, sink, backsplash About 3 to 5 weeks on site, mostly waiting on the countertop Our experience; IKEA phase times below
Full remodel, same layout Plus flooring, lighting, outlets, paint 6 to 12 weeks Fixr
Layout change or walls moved Plus plumbing moves, framing, permits 3 to 8 months Fixr

Still deciding on scope? Our guide to whether a kitchen remodel adds value compares minor and major remodels.

What Order Should a Kitchen Remodel Go In?

A kitchen remodel goes in this order: plan and measure, design, order the cabinets, demolish, rough in plumbing and electrical, pass inspection, close the walls and lay the floor, install cabinets, template and install countertops, then backsplash, appliances and the punch list. Each step needs the one before it finished.

Infographic of the order of a kitchen remodel in twelve numbered steps from measure and design, order cabinets, demolition, rough-in and inspection, walls and floor, cabinet install, countertop template and install, to backsplash, appliances and punch list
The twelve steps in order; the cabinet order comes before demolition, and the countertop only after the cabinets are fastened.

The sequence below follows the phase order in the KraftMaid, IKEA and Fixr guides, with the cabinet order placed before demolition:

  1. Measure and set the budget. Our kitchen measuring guide shows what to capture.
  2. Design and choose finishes. Appliance spec sheets settle the openings; door samples settle the color.
  3. Order the cabinets. This starts the lead-time clock.
  4. Book the trades and the permit. Include the countertop fabricator and, where required, the building permit.
  5. Set up a temporary kitchen and demolish.
  6. Rough-in. Water, drain, circuits, outlet boxes and hood duct, with the walls open.
  7. Rough-in inspection. Where a permit applies, the inspector checks the work before it is covered.
  8. Drywall, paint and flooring.
  9. Deliver, inspect and install the cabinets.
  10. Countertop template, fabrication and install.
  11. Sink, faucet, backsplash and appliances.
  12. Trim and punch list. Crown, toe kick, hardware, touch-ups.

Step 3 causes the most trouble out of place: cabinets ordered after demolition leave a gutted room waiting on a factory.

How Long Does Each Phase Take?

Each on-site phase of a kitchen remodel takes from one day to about three weeks: demolition about a day, rough-in one to two weeks, walls and floor about a week, cabinet installation two to three days, and countertops two to three weeks from purchase to install. Those are the phase times IKEA publishes for its kitchen projects.

The table sets IKEA's figures beside Fixr's; where they disagree, plan on the longer one.

Phase IKEA Fixr What holds it up
Demolition One day 1 to 3 weeks Mold, rot or hazardous materials behind the old boxes
Rough-in (plumbing, electrical) One to two weeks, with wall repair and flooring Two to four days of electrical and plumbing work Moving the sink or range; waiting for the inspector
Patch, paint, flooring One week Flooring 1 to 3 days Subfloor repairs; tile cure time
Cabinet installation Two to three days Two to three days for stock cabinets Out-of-level floors and walls; missing fillers or panels
Countertops Two to three weeks, purchase to install Two days to a week after the cabinets, if ordered with them Fabricator's queue; sink and faucet not on site at template
Final plumbing, electrical, backsplash One week Backsplash a couple of days Appliance delivery dates
Punch list and cleanup One week No longer than a day for cleanup Damaged or wrong parts found late

The table leaves out the gaps between trades. In our experience those gaps, plus the inspector's calendar, are why three weeks of labor take six to eight weeks on the calendar.

The phases also overlap less than people hope. Rough-in can't start until demolition opens the walls, drywall can't close them until inspection, and the countertop can't be measured until the cabinets are set. That chain is the critical path.

When Should You Order Kitchen Cabinets?

Order kitchen cabinets as soon as the design and appliance choices are final, and before demolition starts, so the boxes arrive while rough-in is still underway. Count the cabinet line's shipment time plus freight transit back from the week you want to install.

With a 6-to-8-week line, for example, place the order about 10 weeks before install day, which covers 8 weeks of production, up to 7 business days of freight and 2 days of acclimation. A 2-week stock line needs about 4 weeks by the same count.

Shipment times for the lines we sell vary from a few business days to about two months:

Cabinet line Typical shipment time
Modernform stock 3 to 5 business days
US Cabinet Depot About 3 business days flat-pack, about 5 assembled
KCD, Tribeca, J&K Cabinetry 7 to 10 days
Fabuwood stock series (Galaxy, Luna, Quest and others), Mantra Typically 2 weeks
NOMA Typically 3 to 4 weeks
St. Martin (Heritage, Vista) Typically 4 to 6 weeks
Diamond, Decorá, Fabuwood custom paint Typically 6 to 8 weeks

Freight comes on top of that. Our shipping policy puts continental U.S. transit at typically 1 to 7 business days by LTL freight, confirmed on your quote. The carrier calls 24 to 48 hours ahead, and standard delivery is curbside.

Two more allowances belong in the plan. Unpack and inspect within 48 hours, and report any damage with photos within 5 days of delivery and before installation (48 hours for Modernform). Then let the cabinets acclimate in the room for 48 hours before they go on the wall, as our shipping FAQ asks.

The order itself has one rule that shapes the timeline: cabinets are made to order, and the sale is final once submitted. Cancelling before production is possible only if the manufacturer accepts it, with a restocking fee of typically 30%. Lock the layout before you order. Our guide to ordering cabinets online covers checkout, and fast lead-time cabinets by brand compares every line's speed.

Week-by-Week: A Stock-Cabinet Kitchen

A remodel with stock cabinets, such as Fabuwood Galaxy in a stock finish like Frost, runs about 10 weeks from the first measurement to the punch list when the layout stays put. The cabinets typically ship in 2 weeks, so the order can wait until the design is final.

This sample assumes a same-layout kitchen, a contractor booked in advance, a permit with a rough-in inspection, and on-site phase times near the slow end of IKEA's figures, with the countertop fabricator booked in advance.

Week What happens Why then
1 Measure; request a free design; order door samples; shortlist appliances A designer's first reply comes within 2 business days
2 Design and itemized quote back (24 to 48 hours after measurements); revisions; approve and order; permit application filed Appliance specs fix the cabinet openings, so they are chosen first
3 Cabinets in production; permit issued; temporary kitchen set up; demolition at week's end Galaxy ships in typically 2 weeks, so demolition can start now
4 Rough-in plumbing and electrical Walls are open; the cabinet drawing shows where every outlet and line goes
5 Rough-in inspection; cabinets arrive (transit 1 to 7 business days, so slow freight can slip this to week 6); inspect and report damage Boxes on site before the walls close, so missing parts surface early
6 Drywall, paint, flooring; cabinets acclimate in the room Painting before cabinets is faster than cutting in around them
7 Cabinet installation (2 to 3 days); countertop template at week's end The fabricator needs fastened, level boxes and the sink on site
8 to 9 Countertop fabrication; trim, crown, toe kick and hardware meanwhile Caesarstone puts fabrication at 7 to 10 days for a very customized job
9 Countertop install; sink, faucet and dishwasher connected The kitchen has water again
10 Backsplash, appliance hookups, punch list Tile follows the counter so it sits on the finished top

In this plan the kitchen is out of service from week 3 to week 9, about six weeks. The fabrication figure is Caesarstone's guidance for a very customized job (simpler projects can take 1 to 2 days); your fabricator's queue can add to it.

A faster line, like US Cabinet Depot, barely shortens this schedule: rough-in and countertops were the critical path, not the cabinets.

Week-by-Week: A Built-to-Order Kitchen

A remodel with built-to-order cabinets, such as Diamond or Decorá, runs about 15 weeks from the first measurement, because the cabinets typically take 6 to 8 weeks to ship. The trick is to keep cooking in the old kitchen through most of that wait.

Fabuwood custom paint (typically 6 to 8 weeks) follows the same shape; St. Martin (typically 4 to 6 weeks) compresses the middle. The table assumes the order ships about 7 weeks after it is placed, mid-window; at the full 8 weeks plus slow freight, add about a week.

Week What happens Why then
1 to 2 Measure, design, samples, appliance choices; approve and order by end of week 2 Every week of indecision here is a week added at the end
3 to 9 Cabinets in production; permit filed; trades and fabricator booked; old kitchen still in use Nothing on site depends on the cabinets yet
8 or 9 Ship date confirmed; temporary kitchen set up; demolition Demolish only once the order has a ship date
9 to 10 Rough-in and inspection Runs while the cabinets are in transit
10 to 11 Cabinets arrive; inspect and report damage; drywall, paint, flooring; acclimate The room is ready the week the boxes are
12 Cabinet installation; countertop template Same chain as the stock plan from here
13 to 14 Fabrication; trim and hardware; countertop install and plumbing The counter sets the end date
15 Backsplash, appliances, punch list Finish work

The kitchen is out of service from about week 8 to week 14, roughly the same six weeks as the stock plan. The longer lead time moved the finish date, not the weeks without a kitchen.

The trap is demolishing on the day you order. Do that with a 6-to-8-week line and the room sits gutted for most of two months. Our cabinets for remodelers page covers the contractor's side.

Stock or Built-to-Order: Which Schedule Fits?

A stock cabinet line fits a remodel with a fixed deadline or a late decision; a built-to-order line fits when you want a specific construction, finish or modification and can order two months ahead.

Infographic comparing two kitchen remodel schedules as horizontal bars: stock cabinets about 10 weeks with demolition in week 3, built-to-order cabinets about 15 weeks with demolition in week 8, both with about 6 weeks without a kitchen
A slower cabinet line moves the finish date, not the weeks without a kitchen, if demolition waits for a ship date.
Question Stock line (Fabuwood Galaxy) Built-to-order (Diamond, Decorá)
Typical shipment time 2 weeks 6 to 8 weeks
Sample schedule, first measure to punch list About 10 weeks About 15 weeks
Weeks without a working kitchen About 6 About 6, if demolition waits for a ship date
Best for Deadlines, rentals, flips, quick decisions Finishes, door styles and modifications a stock line doesn't offer

The difference between the tiers is explained in our stock vs semi-custom vs custom cabinets guide. Assembled or flat-pack matters too: RTA boxes add assembly days to the install, which our RTA vs pre-assembled comparison weighs.

Where Do Permits and Inspections Fit?

Permits normally come before demolition and inspections come before the walls close: the model International Residential Code (section R109.1.2) requires a rough inspection of plumbing, mechanical, gas and electrical work before it is covered or concealed, and local building departments, which adopt and amend that code, set the details.

Kitchen at the rough-in stage: open wall studs with new water supply and drain lines at the sink wall, new electrical boxes and cable at counter height, and a clean subfloor in bright daylight
Rough-in with the walls open: the plumbing and wiring an inspector checks before drywall covers it.

Whether a cabinet swap needs a permit at all depends on where you live. Our Florida cabinet permit guide shows how one state handles it.

For the schedule, two things matter. Ask the department how far out permit review and inspections are booking before you set a demolition date. Then plan the rough-in so the inspector sees it complete in one visit; a failed inspection means another wait for the next opening.

Settle new counter outlets or plug mold on the cabinet drawing before rough-in; our under-cabinet outlet guide covers the options.

How Long Does It Take to Install Kitchen Cabinets?

Installing kitchen cabinets takes about two to three days for a typical kitchen, according to both IKEA and Fixr, once the room is painted and the floor is down. Large kitchens, islands, crown molding and out-of-level floors add days.

Captivating Cabinets sells and ships cabinets to the 48 contiguous states; we do not install them. In New Jersey, installation is available through our sister company, Captivating Construction Group. Everywhere else, your own contractor or installer handles it, and our cabinet installation cost guide explains how they price the job.

Book the installer for a date after the cabinets arrive, not on the delivery date. The 48-hour inspection and 48-hour acclimation windows fit between the two, and a damaged box found before installation is a freight claim, not a schedule crisis.

Doing it yourself takes longer; our DIY cabinet installation guide lays out the work.

Why Do Countertops Come After the Cabinets?

Countertops come after the cabinets because the fabricator measures the installed boxes: Cambria's installation FAQ says all cabinets must be permanently installed and in the same plane before templating. The sink, faucet and appliances should be on site for that measurement too.

Countertop template strips of thin white plastic laid on top of newly installed white shaker base cabinets around a sink base, with the sink and faucet boxes waiting nearby
Template day: the fabricator measures the fastened cabinets, with the sink and faucet already on site.

From template to install, the slab spends most of its time in the shop. Caesarstone tells buyers to expect a 7 to 10 day fabrication timeline for a very customized job, and IKEA puts custom countertops, which a third party installs, at two to three weeks from purchase to install.

Book the fabricator before demolition and have the sink and faucet in the house before the cabinets go in.

Still choosing a material? Our countertop types and heights guide compares them.

How Long Will You Be Without a Kitchen?

You will be without a working kitchen for about four to six weeks in a typical same-layout remodel, from demolition until the countertop and sink go in. That is our arithmetic from the IKEA phase times above; both sample schedules land at the long end, about six weeks.

The sink is the milestone that matters: it goes out on demolition day and returns only after the new top is set.

A temporary kitchen makes those weeks livable. Set it up before demolition, in a room with a sink or near a bathroom:

  • A countertop microwave, an electric kettle and a plug-in induction burner or slow cooker
  • The old refrigerator, if it is staying, moved to a garage or dining room outlet
  • Paper plates and one washing-up bin

What Delays a Kitchen Remodel Most?

Most kitchen remodel delays come from decisions made late, not slow work: changes after the cabinets are ordered, appliances chosen after the openings are drawn, and a sink or faucet missing at countertop template.

Fixr says mold remediation alone can add about a week to demolition. The delays we see most often are avoidable:

  • Changing the layout after ordering. The order is final once submitted, so a change usually means a new order and a new lead time on top.
  • Choosing appliances last. A range or fridge an inch off the drawing can mean a new cabinet.
  • Booking trades in sequence instead of in advance. Calling the fabricator only after the cabinets are in adds their whole queue to the end.

Order door samples early to take one decision off the critical path. Our guide to cabinet door samples covers how to judge them.

Frequently Asked Questions

How long does a full kitchen remodel take from start to finish?

A full kitchen remodel takes about 6 to 12 weeks of construction, according to Fixr, plus design and ordering. Counted from the first measurement, our sample schedules run about 10 weeks with a stock line and about 15 with a built-to-order line.

What is the correct order of a kitchen remodel?

The correct order is plan, design, order cabinets, demolish, rough in, pass inspection, close the walls and floor, install cabinets, then countertops, backsplash, appliances and the punch list. Ordering cabinets before demolition saves the most time.

How far in advance should I order kitchen cabinets?

Order kitchen cabinets at least the line's shipment time plus up to 7 business days of transit before you want to install them. That is typically 2 weeks plus transit for Fabuwood stock series and 6 to 8 weeks plus transit for Diamond, Decorá and Fabuwood custom paint.

How long does it take to install kitchen cabinets?

Installing kitchen cabinets takes about two to three days for a typical kitchen, per IKEA and Fixr. We do not install; your contractor does, or Captivating Construction Group in New Jersey.

How long does it take to replace kitchen cabinets and countertops?

Replacing kitchen cabinets and countertops in the same layout takes about 3 to 5 weeks on site in our experience, most of it waiting on the countertop. The cabinets go in over two to three days; the top is then templated on them and fabricated, which IKEA puts at two to three weeks from purchase to install. Add the cabinet line's shipment time before all of it.

When should I order appliances for a kitchen remodel?

Choose appliances before you order the cabinets, and have them on site by countertop template day. Their spec sheets fix the cabinet openings, and Cambria's installation FAQ asks for the sink, faucet and appliances to be there at the final measurement. Ask the retailer for delivery dates when you buy.

Do floors go in before or after kitchen cabinets?

Floors can go either way, depending on the flooring. IKEA's timeline puts most flooring in before the cabinets but says a floating floor should go in after them. Ask your installer which suits your floor.

How long after cabinets are installed are countertops installed?

Countertops are usually installed anywhere from a few days to about three weeks after the cabinets. Fixr says two days to a week when the top was ordered with the cabinets; IKEA gives custom tops two to three weeks from purchase. The fabricator's queue sets the date.

Can a kitchen remodel be done in two weeks?

A full kitchen remodel rarely finishes in two weeks, because a stone countertop can only be templated once the cabinets are set, and fabrication of a customized top takes 7 to 10 days, per Caesarstone. A cosmetic update (paint, hardware, lighting) can fit in that window.

Why are there days when nobody is working on my kitchen?

Quiet days in a kitchen remodel are usually waits built into the sequence: the inspector's visit, the countertop in the fabricator's shop, or the next trade's opening. Rough-in can't be covered until it passes, and the counter can't go in until a top cut to your installed cabinets is ready. Booking the fabricator and inspector early shortens those gaps.

Can I live in my house during a kitchen remodel?

Most people live at home through a kitchen remodel and cook in a temporary kitchen for about four to six weeks. In our experience, moving out is rarely needed unless other rooms are being remodeled too.

Start the Clock With a Free Design

Send us your room's measurements, appliance choices and a target install month, and our free 3D design service will reply within two business days, then return renderings and an itemized quote within 24 to 48 hours of getting your measurements, with the line's shipment time on it. You can also order a Fabuwood door sample for $35 (samples are final sale) while you decide.

We design, quote and ship cabinets to the lower 48 states; we do not install them. Questions about timing? Contact us or call (609) 900-3358.

Sources: Fixr, "How Long Does a Kitchen Remodel Take?"; KraftMaid, "Steps of a Kitchen Remodel"; IKEA US, "Kitchen Remodel Timeline"; Houzz, 2024 U.S. Houzz & Home Study (2023 projects); Cambria, Installation FAQ; Caesarstone US, "The Fabrication Series"; International Residential Code section R109.1.2 as summarized by Jaspector; Captivating Cabinets shipping policy and shipping FAQ. Shipment times are typical, not guaranteed, and your quote confirms them. Sample schedules and the without-a-kitchen estimate are our own arithmetic.

Found this useful? Share it
Add as a preferred source on Google
Noor K.

Written by

Noor K.

Technology Manager at Captivating Cabinets

Noor manages and develops the Captivating Cabinets website, and writes practical guides on cabinet styles, finishes, pricing, and remodel planning.

Your Cart

Your cart is empty.

Browse cabinets →
Free · No obligation

See your new kitchen before you spend a dollar

Send rough measurements and a few photos. A designer replies within 2 business days, and you get photorealistic 3D renderings with an itemized quote in 24–48 hours.

Contractors get trade pricing. Have a quick question? Ask Cabinets AI →

Kitchen designed with the free 3D design service from Captivating Cabinets